Fair comparison: flex the budget before you judge performance

ACCA Management Accounting6 min readFree sample

20modules
141syllabus outcomes
2timed mock exams
Freesample lesson
Step 1 of 5

Meet the problem

Meet Elena

Elena runs a small bakery. She planned to bake 1,000 loaves this month and sold 1,200. Her costs came out well above the plan. Did she lose control of costs, or just sell more bread?

In simple words
  • A budget is a plan for one level of activity.
  • Flexing recalculates the plan for the activity that really happened.
  • Only then can a cost gap be called good or bad.

You already know: You already do this at home: if you drove twice as far, you would expect to spend twice as much on fuel. You would not call that overspending.

The idea in plain words

✗ Original budget onlyCosts 700 over the planBlames Elena for selling more.
! Ignore the gapSales were up, so all is wellMisses a real cost problem.
✓ Flex, then compareCosts 300 over the flexed budgetShows the part worth investigating.

Flexing the budget in four steps

A

Split costs

Variable or fixed

B

Use actual activity

Replace the planned units

C

Flex the budget

Scale revenue and variable costs

D

Compare

Actual against flexed, line by line

Same activity on both sides, so the gap means something.

Elena's month

✗ Before

Variable costs are 700 over budget, so the bakery wasted money.

Fix it step by step

A2 a loaf variable; 1,000 fixedSplit costs
B1,200 loavesUse actual activity
Cprofit 2,600Flex the budget
D300 adverseCompare
✓ After

Against the flexed budget, variable costs are 300 over. I will find out why each loaf cost more than planned.

What flexing gives Elena

Fairness

Extra sales are not treated as a cost failure.

Focus

The real gap is 300, not 700.

Action

She knows exactly what to investigate.

Try it and remember

Myth

If actual costs are above the budget, the manager overspent.

Fact

Costs may simply have risen because activity rose. Flex first.

Your turn. Think of a cost at your workplace that changes with activity. If activity were 10 percent higher than planned, what would you expect that cost to do before you called it overspent?

Check yourself

1Which costs change when a budget is flexed?

Answer: Variable costs and revenue, which move with activity. Fixed costs stay as budgeted.

2Why compare actual results with the flexed budget instead of the original budget?

Answer: It compares like with like, so the gap shows control of costs rather than a change in activity.

3In the example, what do the extra 300 of variable costs against the flexed budget tell Elena?

Answer: Costs per loaf were higher than planned, so she should investigate the cause.

Remember
  • Flex the budget to actual activity before comparing.
  • Variable costs and revenue move; fixed costs stay.
  • Compare actual with flexed to find what needs attention.