Elena runs a small bakery. She planned to bake 1,000 loaves this month and sold 1,200. Her costs came out well above the plan. Did she lose control of costs, or just sell more bread?
Meet the problem
- A budget is a plan for one level of activity.
- Flexing recalculates the plan for the activity that really happened.
- Only then can a cost gap be called good or bad.
You already know: You already do this at home: if you drove twice as far, you would expect to spend twice as much on fuel. You would not call that overspending.
The idea in plain words
Costs 700 over the planBlames Elena for selling more.
Sales were up, so all is wellMisses a real cost problem.
Costs 300 over the flexed budgetShows the part worth investigating.
Flexing the budget in four steps
Split costs
Variable or fixed
Use actual activity
Replace the planned units
Flex the budget
Scale revenue and variable costs
Compare
Actual against flexed, line by line
Same activity on both sides, so the gap means something.
Elena's month
Variable costs are 700 over budget, so the bakery wasted money.
Fix it step by step
Against the flexed budget, variable costs are 300 over. I will find out why each loaf cost more than planned.
What flexing gives Elena
Fairness
Extra sales are not treated as a cost failure.
Focus
The real gap is 300, not 700.
Action
She knows exactly what to investigate.
Try it and remember
If actual costs are above the budget, the manager overspent.
Costs may simply have risen because activity rose. Flex first.
Check yourself
1Which costs change when a budget is flexed?
Answer: Variable costs and revenue, which move with activity. Fixed costs stay as budgeted.
2Why compare actual results with the flexed budget instead of the original budget?
Answer: It compares like with like, so the gap shows control of costs rather than a change in activity.
3In the example, what do the extra 300 of variable costs against the flexed budget tell Elena?
Answer: Costs per loaf were higher than planned, so she should investigate the cause.
- Flex the budget to actual activity before comparing.
- Variable costs and revenue move; fixed costs stay.
- Compare actual with flexed to find what needs attention.